Reliable Integration Testing ​

The problem: a large integration suite that takes too long and fails for reasons that have nothing to do with the change under test. Rerunning it usually works, which is exactly what makes it corrosive — the suite stops being evidence and becomes a toll.

What you will build: the same suite, split across worker processes, with the shared state that made it flaky isolated per worker, and with the remaining flakiness reported honestly instead of retried away.

This tutorial is written from four real suites — Wolverine's PersistenceTests and Redis.Tests, Polecat's Polecat.Tests, and Bobcat's own — so the failure modes below are what actually broke, not what might.

What this actually buys ​

SuiteTestsSequential4 workersResult
Polecat.Tests1587954s366s (2.6x)1587/1587 after two fixes
Wolverine PersistenceTests78164s73s (2.2x)78/78, no source changes
Wolverine Redis.Tests144452s206s (2.2x)144/144, no source changes

Compute your ceiling before provisioning a fleet. Partitioning is by test class, so a class cannot be split, so the largest class is a floor no worker count goes below:

ceiling = sum(all test durations) / largest class's total duration

Redis is 599s of test time with a 188s compliance class in it — a 3.19x ceiling and a ~188s floor. Measured at 8 workers: 199s. If your ceiling is 3x, asking for 8 workers buys containers and nothing else. When the floor is what binds, the fix is splitting that class or making its tests faster, not adding lanes.

Step 0 — be an MTP host ​

The supervisor drives the test executable over Microsoft.Testing.Platform's server mode. It never loads your test assembly, so your test project needs no reference to Bobcat at all. It does need to be an MTP host rather than an xUnit native runner:

xml
<OutputType>Exe</OutputType>
<UseMicrosoftTestingPlatformRunner>true</UseMicrosoftTestingPlatformRunner>

Check with ./YourTests --list-tests. If that errors with unknown option, you still have the native runner and the supervisor cannot drive it.

This changes only the entry point — dotnet test, --filter, TRX and coverlet keep working.

Put the property in Directory.Build.props, not a per-job -p: override. Same output path, different entry point: a build without it silently produces a non-supervisable executable.

Step 1 — the partitioning contract ​

The supervisor splits by test class, never by individual test. That is a correctness rule rather than a tuning choice — every framework's isolation contract is per class or collection, so a class's fixtures and static state assume one process.

Splitting Wolverine's suite per test failed 1–4 tests non-deterministically. Per class it was 78/78 at the same wall clock. The mechanism was a class whose setup read:

csharp
var schemaName = "sqlserver" + ++count;   // static int

Split across four processes, each restarts at zero and all four collide. Nothing about that is visible in the test list, which is why the rule has to be conservative. You inherit this for free.

Step 2 — isolate resources per worker ​

Class-level partitioning keeps a class together. It cannot stop two different classes that share a database from landing in different workers. So each worker needs its own:

csharp
new MtpWorkerFactory(path)
{
    EnvironmentFor = worker => new Dictionary<string, string>
    {
        ["POLECAT_TESTING_DATABASE"] = connectionStringFor($"polecat_w{worker.Lane}")
    }
}

Lane is bounded by MaxParallelWorkers, so you provision as many databases as workers you asked for. This requires the suite to read its connection string from an environment variable — most already do.

Check first whether you already have this for free. A suite that starts its own container per process — Testcontainers from a [ModuleInitializer], say — already gets a private broker per worker with nothing to wire. That is why Wolverine's Redis tests parallelised with no source changes at all.

Two costs worth knowing rather than discovering: every process pays the container start on the critical path, and nothing reaps those containers if the reaper is off — one orphan per process, which reached 49 on one machine.

Step 3 — expect these three bugs on the first red run ​

All three were found in real suites, all silent, and all are why a first parallel run goes red:

  1. Text-rewriting a connection string instead of using a builder.
  2. Server-scoped names — a schema, a queue, a topic — that are unique per process but not per server.
  3. Environment-dependent test identities, where a test's own name or id changes with the machine or the lane.

The triage order for a red first run, and what a hang or a memory bloat means, is in Making a test suite safe to run in parallel worker processes.

Step 4 — report flakiness instead of hiding it ​

Two mechanisms, and the difference between them matters.

A retry budget lets a scenario pass on a second attempt. The run still exits 0, and the pass-on-retry is reported separately rather than folded into the pass count:

csharp
runner.RetryBudget = new RetryBudget { MaxAttemptsPerTest = 2 };

Watch the pass-on-retry number, not the pass number. A retry budget will mask a rising failure count if nobody is looking at it.

Indeterminate outcomes are reported as indeterminate. When a worker faults, the tests it never reported are not silently dropped and not counted as passes — they come back as indeterminate, with their display names. A suite that cannot tell you what happened should say so.

The committed ledger is where flake and duration history lives across runs, so "this test is flaky" becomes a claim with evidence behind it rather than a memory. It is derived, never primary.

What this does not buy you ​

Parallel workers do not fix a suite whose tests genuinely depend on each other's data. They expose it. That is the point — but it means the first run after you turn this on is a triage exercise, and budgeting for it is the difference between adopting this and abandoning it.

Where to go next ​

Released under the MIT License.